Ford Motor Company in Silverton is losing 720 units a day, or over R500 million, as widespread power losses continue.
Share with friends
Up until now there has been no indication when the plant will be up and running after overhead power lines feeding large parts of Pretoria collapsed and fell on the N4 highway on April 10, resulting in a power outage affecting large parts of Pretoria East.
Neale Hill (President of Ford Motor Company Africa), said in a local television interview that the knock-on effect could prevent the company from reaching its optimal production volumes for months to come.
Exports of the new Ford Ranger will be affected by the power problems in Pretoria.
“Although we have a huge solar power network, it only provides about a quarter of our electricity needs. Certain parts of the manufacturing process require a high-power output at a constant rate to function.
“The outage has also had an impact on our suppliers of whom 15 are located next to our plant in the Tshwane Special Automotive Economic Zone. Other suppliers elsewhere in the country are also affected as we could experience a temporary interruption in the delivery of parts,” he says.
As a result of the incident, all three shifts at the Silverton Plant are currently suspended affecting 5 500 employees and approximately 60 000 jobs across Ford’s local supplier network in producing the Ford Ranger and Volkswagen Amarok bakkies in Silverton.
Ford invested over a billion USD in the new manufacturing plant, which exports bakkies to over 100 markets worldwide. When the plant is at full capacity it will be the biggest plant of its kind manufacturing the Ford Ranger in the world.
Neale Hill, President of Ford Motor Company Africa.
When questioned about Ford reconsidering its position in South Africa, Neale answered that not with the kind of money that Ford has invested and that Ford is committed to the country. “It is, however, getting more difficult doing business in South Africa,” he said during the interview.
Neale said obstacles like load-shedding, and issues surrounding the ports and rail infrastructure make it difficult to sell South Arica as an investment destination.
The initial assessment by the City of Tshwane’s energy and electricity team found that at least seven powerline structures had collapsed and were badly damaged.
A Ford spokesperson said the company was working with both the City of Tshwane and Eskom to resolve the issue, but as yet there is no indication of when power will be fully restored to the facilities.
Volkswagen has expanded the new Tiguan model line-up with the addition of two new engines, a 2.0 TDI with 110kW and a 2.0 TSI with 140kW. Both engines are offered with a 7-speed DSG transmission.
DFSK South Africa announced that effective immediately, DFSK will be extending its warranty offering on its new DSFK KO1S Bakkie and DSFK C35 Panel Van to a 50 000km / 2-year warranty for all new customers ensuring greater peace of mind and customer satisfaction.
The challenge for us is to maintain our Dealer of the Year status in the future as it symbolises the effort we put in to create the best environment for our customers and our staff.
Mahindra South Africa marked two decades of success in the country by hosting the Mahindra Fusion Fest, a landmark event that blended business, culture and community engagement and set the stage for a dynamic third decade, according to the manufacturer.
The SunBet Arena in Pretoria is a hive of activity as Mahindra South Africa finalises preparations for its historic Fusion Fest this Saturday (22 February).
Digi Cars Group, a dealership group in the South African automotive industry, is making an impact at this year’s EidFest, which is taking place at the Gallagher Convention Centre from Thursday, 20 February to Sunday, 23 February 2025.