Hino back in business at Durban plant

Production at Toyota’s plant at Prospecton in Durban is slowly but surely getting back to normality.

Hino restarts production

On the Hino truck side, production is already ramping up to its required output rate after restarting production on 23 May following an enforced shutdown of 40 days resulting from extensive damage caused by the floods that hit KwaZulu-Natal on 11 April.

“This was a wonderful reward for a Herculean effort by a dedicated team, which included three specialists from Hino Motors in Japan who had prior experience in cleaning up and putting into operation factories damaged by tsunamis in Japan,” commented Ernie Trautmann, Vice President of Hino SA.

A total of 78 built-up trucks or completely knocked down kits of components were unsalvageable and will be scrapped and destroyed so that none of these compromised vehicles get to market.

Most of the damage was caused by a wall of water and silt that came down the river next to the plant when the sluices at the overfull Shongweni Dam were opened. The existing canals and drains could manage the initial downpour of rain and also proved effective when the second torrent of heavy flooding hit KZN on May 21.

Celebrations as Toyota restarts Hino production at the Prospecton Manufacturing plant in Durban, KwaZulu-Natal

Cleaning the mud and fine silt from the many pieces of electronic and mechanical equipment in the various production plants has proved to be extremely time-consuming, and the Toyota passenger car and light commercial vehicle production lines are still not operational.

None of the suppliers to the Hino plant were affected, whereas many suppliers supporting the car and LCV plant also suffered extensive damage to their plants and equipment.

Hino lost approximately 550 vehicles out of scheduled production, but the management team is confident they will be able to make up this shortfall by year end.

About 100 assembly line workers went home for the first week after the floods and then returned to the plant in batches during the following weeks to assist in the flood-recovery programme.

“Keeping our customers fully aware of developments in terms of when they could expect delivery of trucks already ordered or when production was expected to restart was a priority for our sales and marketing team.

“We have found our customers to be most understanding of our plight in these challenging times, and we are expediting the process to ensure delivery as soon as possible,” concluded Ernie.

More Industry News stories

Isuzu’s ambitious plans for truck manufacturing in South Africa

Isuzu’s ambitious plans for truck manufacturing in South Africa

Isuzu Motors South Africa is positioning itself to become the primary manufacturing centre for commercial trucks across the African continent, a strategic move that could significantly boost production volumes while increasing the use of locally sourced components.

  • 21 August 2025
Kiara driving change, one pink truck at a time

Kiara driving change, one pink truck at a time

In a move that’s turning heads across the transport industry, Kiara Baijnath (photo), the founder and director of HerWay Logistics, is redefining what it means to be a woman in trucking by adding another pink Mercedes-Benz Actros 2645 to her fleet.

  • 21 August 2025