Back to business for Ranger at Ford plant

Business at Ford’s manufacturing plant in Silverton Pretoria is getting back to normal but the risk of interrupted power supply remains, Ford says.

23 Ford Power Back1

The problems arose when overhead powerlines collapsed over the N4 on 10 April after a huge storm that left large parts of Pretoria, especially in the eastern part of the city, without electricity. This included the Ford plant and related industries in the Ford supply chain.

Production was suspended on 11 April and restored in stages starting on the evening of April 12, when production has slowly resumed.

The estimated total loss of production during the down days was 1 440 units. and a dark picture of the impact of the shutdown for an extended period was sketched by Ford Africa’s president, Neale Hill.

Ford tells Dealerfloor that the scale of the Eskom infrastructure concern holds the risk of interrupted supply. “However, we continue to liaise with Eskom and local government as they work to balance the system and fully restore the network.”

The newly upgraded Silverton plant is currently the second largest in the world producing the new generation Ford Ranger as well as the Volkswagen Amarok, both for local consumption and export to more than 100 markets. More than 700 Ranger pick-ups are manufactured in Pretoria every day utilising three shifts working at the plant.

More Industry News stories

Isuzu reduces carbon emissions while expanding production

Isuzu reduces carbon emissions while expanding production

Isuzu Motors South Africa (IMSAf) has achieved a 38% reduction in Scope 1 and Scope 2 CO₂ emissions compared with its 2013 baseline while increasing vehicle production by 21% during the 2025/26 financial year at its Gqeberha manufacturing facility.

  • 19 November 2026
Fuel security: South Africa's weak links exposed

Fuel security: South Africa's weak links exposed

Diversifying oil supplies, investing in pipelines and rail infrastructure, improving port operations and expanding inland storage facilities are among the measures needed to reduce South Africa's vulnerability to international fuel supply disruptions.

  • 19 November 2026